Resources - Building consent process
Cook Islands building consent process:
There are three forms of sign off you require to build in raro
- Environment – this costs about $20 they don’t do anything but look at the plans and give it a stamp
- Te Marae Ora (Health department) – $80 (I think) they sign off the - Waste water plan – you need this to be completed by a registered plumber
- ICI (Infrastructure Cook Islands) – $120 + (depending on size of house) Building controller sign off - this is the last sing off but remember you have to do the first to steps 1 and 2 first.
https://ici.gov.ck/building-permits/